Summary
Shoreline protection project to construct a previously designed and permitted living shoreline project along approximately 2,000 feet of shoreline at the Arturo Galvan Coastal Park adjacent to the Lower Laguna Madre within the City of Port Isabel. Work will consist of debris removal along the shoreline, shoreline earthwork grading, the construction of two small, low-crested rock breakwaters approximately 1,885 feet long in total, and marsh vegetation transplanting and seeding. The breakwaters will protect an inter-tidal area planted with native low marsh vegetation, in order to help reduce shoreline erosion and stabilize the project shore.Basics
Cameron
N/A
City of Port Isabel
$787,515
Classification
- CMP 306
- CEPRA
Shoreline Protection
Wetlands/Marsh/Habitat Restoration
Timeline
completed
2016
Funding Sources
Source 1
1576
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$467,800
08
2014
Source 2
13-030
Coastal Management Program (CMP)
Secondary
Federal
$219,715
17
2013
Source 3
City of Port Isabel
Secondary
City
$100,000
Contacts
Responsibility
General Land Office
Contact