Galveston Island State Park Marsh Restoration and Protection Phase III

Summary

The GLO shall complete the planning, design, and construction of up to 7,550 linear feet of breakwaters in the Butterowe Bayou, Oak Bayou, and Dana Cove areas, under Galveston Island State Park Marsh Restoration and Protection – Phase III.  Texas Parks and Wildlife Department shall also provide technical support to the GLO during planning, design, and construction of the breakwaters.

Basics

Galveston
N/A
Texas Parks and Wildlife Department
$5,078,115

Classification

  • CEPRA
Habitat Restoration/Protection Wetlands/Marsh/Habitat Restoration

Timeline

completed

Funding Sources

Source 1

National Fish and Wildlife Foundation
Primary
Federal
$5,000,000

Source 2

1637
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$47,790
10
2018

Contacts

Responsibility
General Land Office
Contact
Coastal Resources 800.998.4456 512.475.0773