Summary

The City of South Padre Island will improve Moonlight Circle (Access Point #13) with the installation of an ADA-compliant dune walkover in place of the aging Mobil-mat currently installed. The walkover improvements will include drinking water and rinse stations. Installed plumbing will also be used to irrigate the surrounding dunes when needed.

Basics

Cameron
N/A
City of South Padre Island
$190,000

Classification

  • CMP 306A
Public Access Shoreline Protection

Timeline

completed
2018

Funding Sources

Source 1

16-071
Coastal Management Program (CMP)
Primary
Federal
$95,000
20
2016

Source 2

16-071
City of South Padre Island
Secondary
City
$95,000

Contacts

Responsibility
City of South Padre Island
Contact
Reuben Trevino Coastal Resources Manager 4601 Padre Blvd South Padre Island 956.761.8111 Email