Indian Point East Shoreline Protection Phase 2

Summary

The GLO shall construct Indian Point East Shoreline Erosion Protection project which consists of the construction of approximately 1,800 linear-feet of breakwaters with six segments of 200 to 500 feet with 30-foot gaps, extending from the shoreline revetment.

Basics

Nueces
N/A
Coastal Bend Bays & Estuaries Program
$2,194,539

Classification

  • CEPRA
  • Other
Shoreline Protection

Timeline

completed

Funding Sources

Source 1

1660
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$5,000
10
2018

Source 2

NRDA
Other
Other
$2,189,539

Contacts

Responsibility
General Land Office
Contact
Coastal Resources 800.998.4456 512.475.0773