Summary
Project to modify the Keith Lake Fish Pass through the construction of a rock baffle in the middle of the fish pass to assist in providing conservation of the vast marsh south of the GIWW adjacent to state highway 87 in Jefferson County as one phase of a project to restore the hydrologic pattern of the marsh system to pre-development conditions. The baffle will reduce the cross section of the Keith Lake Fish Pass, so as to reduce the velocity of the water through the pass and thereby decrease the salinity within Keith Lake. The local project partner, Jefferson County, is taking the project lead and is responsible for overall execution of the project. Construction began in early January 2015.
Basics
Jefferson
N/A
Jefferson County
$5,102,000
Classification
- CEPRA
Wetlands/Marsh/Habitat Restoration
Timeline
completed
2015
Funding Sources
Source 1
1577
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$1,890,000
08
2015
Source 2
Jefferson County
Secondary
County
$712,000
Source 3
Texas Parks and Wildlife Foundation
Primary
State
$1,250,000
Source 4
Sempra
Secondary
Other
$625,000
Source 5
Golden Pass
Secondary
Other
$625,000
Contacts
Responsibility
General Land Office
Contact