GIWW-Rollover Bay Reach Beneficial Use of Dredged Material FY2015 & FY2016 events

Summary

Beach nourishment project beneficially utilizing approximately 171,000 cubic yards of material dredged from the fall-winter 2014 U.S. Army Corps of Engineers maintenance dredging of the Gulf Intracoastal Waterway (GIWW) Rollover Bay Reach and placement along approximately 102,000 linear feet of Caplen Beach just west of Rollover Pass. Work was completed in mid-February 2015.

Basics

Galveston
N/A
Galveston County
$6,419,000

Classification

  • CEPRA
Beach Nourishment with Beneficial use of Dredged Material

Timeline

completed
2016

Funding Sources

Source 1

1608
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$157,500
08
2015

Source 2

United States Army Corps of Engineers (USACE)
Other
Other
$5,880,000

Source 3

Galveston County
Secondary
County
$52,500

Contacts

Responsibility
General Land Office
Contact
Coastal Resources 1.800.998.4456 512.475.0773