Summary
During Cycle 3, preliminary engineering and permitting tasks were conducted for a beach nourishment project that will restore the eroded beach at the City of Jamaica Beach on Galveston Island. Because construction was postponed until after the 2005 turtle-nesting season, the construction phase of the project was carried forward into Cycle 4. The dune restoration phase of the project was completed in August of 2006. The beach nourishment phase could not be constructed during Cycle 4 due to sand source and USACE permit issues.
Basics
Galveston
N/A
City of Jamaica Beach
$1,066,667
Classification
- CEPRA
Beach Nourishment
Dune Restoration
Timeline
completed
Funding Sources
Source 1
1214
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$800,000
03
Source 2
1214
City of Jamaica Beach
Secondary
City
$266,667
03
Related Projects
Contacts
Responsibility
General Land Office
Contact