Summary
This project restored portions of a revetment damaged by Hurricane Ike back to their original post-construction state. The revetment was installed along 6,000 feet of shoreline adjacent to the Corpus Christi Ship Channel and jetties at the mouth of Piper Channel near Port Aransas during the Cycle 5 phase of a phased shoreline protection program that began in Cycle 1 and continued through Cycles 2, 3, 4 and 5. Over 2,000 acres of wetland habitat at the Port Aransas Nature Preserve are being protected by this erosion response project.
Basics
Nueces
N/A
City of Port Aransas
$1,359,235
Classification
- CEPRA
Shoreline Protection
Wetlands/Marsh/Habitat Restoration
Timeline
completed
2013
Funding Sources
Source 1
1463
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$81,554
06
2010
Source 2
1463
Federal Emergency Management Agency (FEMA)
Primary
Federal
$1,223,312
Source 3
1463
City of Port Aransas
Secondary
City
$54,369
Contacts
Responsibility
General Land Office
Contact