Fulton Park Shoreline Access Project

Summary

The town constructed a reinforced cinderblock structure with restroom facilities that include sinks and two stalls in both men's and women's areas.  A metal roof was installed over a heavy-duty timber structure to withstand the coastal elements. The drinking water fountains was constructed on the exterior of the building to provide free access to water at any time of the day.  All facilities are fully accessible to handicapped individuals.

Basics

Aransas
N/A
City of Fulton
$89,920

Classification

  • CMP 306A
Public Access

Timeline

completed

Funding Sources

Source 1

04-028
Coastal Management Program (CMP)
Primary
Federal
$53,952
08

Source 2

04-028
City of Fulton
Secondary
City
$35,968
08

Contacts

Responsibility
General Land Office
Contact
Coastal Resources 800.998.4456 512.475.0773
Responsibility
City of Fulton
Contact
Ms. Kathy Railsback Project Manager P.O. Box 1130 Fulton, Texas 78358-1130 361.729.5533 361.729.7029 Email