Summary
Beach nourishment project beneficially utilizing approximately 750,000 cubic yards of material dredged from the U.S. Army Corps of Engineers maintenance dredging of the Galveston Ship Channel and placement along the seawall beginning at 61st Street and continuing westward to 103rd Street.Basics
Galveston
N/A
City of Galveston Park Board
$23,943,358
Classification
- CEPRA
Beach Nourishment with Beneficial use of Dredged Material
Timeline
completed
2015
Funding Sources
Source 1
1609
Coastal Erosion Planning and Response Act (CEPRA)
Secondary
State
$2,000,000
08
2015
Source 2
City of Galveston Park Board of Trustees
Primary
City
$4,500,000
Source 3
United States Army Corps of Engineers (USACE)
Other
Federal
$4,180,800