Notice and Opportunity to Comment on Requests for Consistency: Cape Velero Home Owners Association

On January 10, 1997, the State of Texas received federal approval of the Coastal Management Program (CMP) (62 Federal Register pp. 1439 - 1440). Under federal law, federal agency activities and actions affecting the Texas coastal zone must be consistent with the CMP goals and policies identified in 31 TAC Chapter 26. Requests for federal consistency review were deemed administratively complete for the following project(s) during the period of March 10, 2025 to March 14, 2025.  As required by federal law, the public is given an opportunity to comment on the consistency of proposed activities in the coastal zone undertaken or authorized by federal agencies.  Pursuant to 31 TAC §§30.20(f), 30.30(h), and 30.40(e), the public comment period extends 30 days from the date published on the Texas General Land Office web site. The notice was published on the web site on Friday, March 27, 2025. The public comment period for this project will close at 5:00 p.m. on Sunday, May  4, 2025.

Federal License and Permit Activities:

Applicant: Cape Velero Home Owners Association

Location: The project site is located in Port Bay, within an existing dredged canal and along the south and southwest shores of the Cape Velero Estates Development approximately 3 miles west of Rockport, Aransas County, Texas.

Latitude and Longitude: 

Canal Latitude: 28.04033, -97.12442

DMPA 1 (upland, 1.3 acres) 28.04321, -97.12712

DMPA 2 (upland, 2.3 acres) 28.04545, -97.12324

Channel/Breakwater 28.03950, -97.12780

Reef Ball Breakwater East End 28.03927, -97.12637

Reef Ball Breakwater West End 28.03954, -97.12758

Project Description: This permit request was originally submitted for Public Notice on May 24, 2023 and withdrawn by the applicant on July 17, 2023. After review of the comments received during the initial Public Notice and modification to the previous design and draft mitigation plan, the applicant is requesting a permit for the following: 

The applicant proposes to conduct maintenance dredging of 1.17 acres of an existing boat launch basin and boat canal. The boat launch basin and canal fronting the Cape Velero subdivision was originally excavated in the mid-1980s. The existing canal/basin area would be dredged to a depth of -3.0 feet mean sea level (MSL) and would yield an estimated 6,356 cubic yards (CY) of dredged material. In addition, the applicant proposes to establish a dredged-and-marked 30-foot-wide by 150-foot-long access channel into Port Bay from the existing boat canal. The proposed channel would confine boat traffic to a single channel until reaching navigable depths in Port Bay, thus minimizing possible seagrass and bay bottom damage by boat traffic where no channel currently exists. The proposed channel would have a 2- by 240-foot limestone breakwater installed on the 

southeast side to reduce wave energy and bay bottom creep, and to minimize sedimentation and reduce the frequency of future maintenance dredging requirements. This feature would affect 480 square feet of bay bottom. Four 8-inch-diameter pilings would be installed at 37-foot intervals along the edge of the breakwater as markers to aid navigation. The proposed 0.11-acre boat access channel would be dredged to a depth of -3.0 feet MSL. The calculated dredge material volume would be 292 CY of material for the boat access channel, for a total amount of 6,648 CY of material for the project.

The dredged material would be mechanically excavated using a Wilco amphibious excavator. The contractor unit is 16 feet wide and 32 feet long with two (2) 5-foot-wide pontoons and weighs 58,000 pounds. The drive system is hydraulic, powered by the Caterpillar 330 Excavator engine and hydraulic system, and has pyramid or flotation shoes on the drive system. This excavator floats in -4.5 feet of water and has a 50-foot operating reach. Dredging would start at the launch ramp basin and then proceed out the boat canal toward the open waters of Port Bay. Initially, the dredged material would be placed within a ring of hay bales on the uplands adjacent to the boat basin for dewatering until the excavator is beyond reach of the shoreline. A backhoe onshore would transfer 

the dewatered material to a dump truck that would transport the material to one of two upland disposal areas for unloading and leveling. Silt fencing would be utilized at the upland placement areas to hold the material in place until stabilized. When dredging beyond reach of the boat basin shoreline, and through the extent of the boat canal and proposed channel into Port Bay, the dredged materials would be placed on a set of small barges with sidewalls. When barge loading capacity is reached, the individual barges would be pushed by a small outboard motor to the launch ramp and offloaded by backhoe into dump trucks. The dump trucks would relay the material to the upland disposal areas for unloading and leveling. Weighted sediment curtains would be used when working in open waters to minimize turbidity outside the work area. After the material has been 

placed within the upland disposal areas and one to two weeks of drying time has occurred, a small bulldozer would spread the material evenly within the disposal area. Based upon the anticipated dredge volume, an approximate 1-foot layer of material would be spread within each of the disposal areas. Once settling and conditioning of the materials is achieved over several months, the disposal areas would be seeded with a native grass species mix to establish vegetative cover.

The applicant also proposes to install fourteen breakwater structures 18 to 60 feet in length, consisting of a double row of 36-inch diameter reef balls installed on a staggered 3-foot offset with 15-foot wide front line gaps and 10-foot wide closure gaps, using approximately 148 reef balls, as part of the proposed mitigation plan described in the Mitigation section of this document. 

In addition, the project would include launch ramp improvements through the addition of a 4- by-25-foot wing pier; a 4- by-60-foot walkway, and three 3- by-20-foot finger piers. Approximately 5,615 square feet of submerged widgeon grass (Ruppia maritima) and a minor occurrence of turtle grass (Thalassia testudinum), found in small patches within the existing canal and within the proposed 0.11-acre boat access channel, would be directly impacted from the dredging and placement of the channel breakwater as currently proposed. No oysters were observed within the footprint of the project’s proposed work area.

MITIGATION: Out of Kind – On-Site mitigation is offered to offset the seagrass impacts summarized above. Mitigation would consist of installing fourteen breakwater structures 18 to 60 feet in length, consisting of a double row of 36-inch diameter reef balls installed on a staggered 3-foot offset with 15-foot wide front line gaps and 10-foot wide closure gaps, using approximately 148 reef balls. This breakwater system would dissipate wave energy from the prevailing winds that impact this impaired shoreline and slow or stop scouring of the nearshore water bottom. The shadow effect of the breakwater should allow for the expansion and/or establishment of submerged aquatic vegetation in the shadow of the breakwater within the bare bay bottoms fronting the wetland shoreline, and bare bottoms within the shallow waters behind the wetland shoreline. This action is expected to restore water quality and aquatic function through the re-colonization of seagrasses within the wave energy shadow. The placement of the breakwater would be aligned where areas of bare bay bottom interface with existing submerged aquatic vegetation. An indirect effect of the breakwater would be to slow or stop the continuing loss of the emergent wetlands downwind of the structure and potentially allow for some recovery. The mitigation objective is to compensate for direct impact to submerged aquatic vegetation (SAV), primarily widgeon grass (Ruppia maritima), and a minor occurrence of turtle grass (Thalassia testudinum), assessed at a total of 5,615 square feet, at a minimum compensatory mitigation ratio of 3:1. The objective would be accomplished by creating improvement in water quality conditions at the mitigation site that results in a minimum increase of 16,845 square feet of additional SAV-covered submerged lands through expansion and colonization of existing SAV resources.

Type of Application: U.S. Army Corps of Engineers permit application #SWG-2005-00696. This application will be reviewed pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act. Note: The consistency review for this project may be conducted by the Texas Commission on Environmental Quality as part of its certification under §401 of the Clean Water Act.   

CMP Project No: 25-1152-F1

Further information on the applications listed above, including a copy of the consistency certifications or consistency determinations for inspection, may be obtained from the Texas General Land Office Public Information Officer at 1700 N. Congress Avenue, Austin, Texas 78701, or via email at pialegal@glo.texas.gov. Comments should be sent to the Texas General Land Office Coastal Management Program Coordinator at the above address or via email at federal.consistency@glo.texas.gov.

Send a comment about this notice to the GLO

With few exceptions, an individual is entitled on request to be informed about the information that the state governmental body collects about the individual. Under Sections 552.021 and 552.023 of the Texas Government Code, the individual is entitled to receive and review the information. Under Section 559.004 of the Texas Government Code, the individual is entitled to have the state governmental body correct information about the individual that is incorrect.