Adolph Thomae Park Shoreline Protection Phase 3

Summary

Project will address the erosion of approximately 620 feet of the Arroyo Colorado shoreline adjacent to Adolph Thomae County Park.  If these corrective measure to stabilize the existing shreline are not taken, parks facilities and infrastructure will remain in critical danger of being lost due to vessel traffic, flooding and strom surges.  Continual impact cuased by these actions could compromise recreational opportunities for this area and for thousands of visitors.

Phase II construction includes permitting, final design, biddin, engineering services during construction, construction services, and post-project monitoring.

Basics

Cameron
N/A
Cameron County
$700,000

Classification

  • CEPRA
Shoreline Protection

Timeline

completed

Funding Sources

Source 1

1650
Coastal Erosion Planning and Response Act (CEPRA)
Primary
State
$420,000
10
2019

Source 2

Cameron County
Secondary
Other
$280,000

Contacts

Responsibility
General Land Office
Contact
Coastal Resources 800.998.4456 512.475.0773